Traffic Signal, Pedestrian & Bicycle Improvements

  • Project value$989,898.00
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 15, 2024
Prairie Ave at 10th & 11th location map

Project Update 11/4/2024

  • Removals, Concrete work, and Underground Signal work have been completed. Some site restoration Concrete has been poured for the ramps, sidewalk, fillets, and the traffic signal bases and controller cabinet foundation.
  • Signal Equipment has started to arrive and will be assembled and installed over the next couple weeks. Expected final completion is November 22, 2024.

Commuter Route Information

  • Intermittent lane closures are to be expected while installing overhead signal equipment.

Project Milestones

Prairie Avenue & 10th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration

Prairie Avenue & 11th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration