10th Street/Pettigrew Neighborhood Street and Utility Improvements

  • Project value$2,544,126.50
  • Contractor nameAsphalt Surfacing Co.
  • Completion DateNovember 15, 2024

Project Update 11/4/2024

  • Phase 1 and 2 are now complete. 10th Street from West to Menlo Avenue is currently open to thru traffic.
  • Phase 3 paving has been completed.  Covell Street will be open to thru traffic once lighting and restoration work is complete.
  • Phase 4 utility work is complete.  Subgrade stabilization, aggregate base course placement, concrete installation and asphalt paving to be completed in the upcoming weeks.

Commuter Route Information:

  • 10th Street from West Avenue to Menlo Avenue is now open to thru traffic.
  • Covell Avenue from 10th Street to 11th Street is currently closed to thru traffic.
  • Menlo Avenue from 9th Street to 10th Street is currently closed to thru traffic.
  • Pedestrian access is available along the sidewalks.  Please use caution when walking through the work area.

 

10th Street Phases

Project Milestones

Phase 1: 10th Street – West Ave to Euclid Ave

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Traffic Striping
  8. Restoration

Phase 2: 10th Street – Euclid Ave to Menlo Ave

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Traffic Striping
  8. Restoration

Phase 3: Covell Ave – 11th to 10th Street

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Restoration

Phase 4: Menlo Ave – 10th to 9th Street

  1. Removals
  2. Water main
  3. Concrete work
  4. Lighting
  5. Street paving
  6. Restoration